The brief
The location and the platform changed in the same move
Kirby’s branches and remote users work on systems that were hosted in an on-site server room. Moving those systems into a Sydney data centre was also the point at which the virtualisation platform changed, from VMware to Microsoft Hyper-V.
Branch connectivity, remote access and the other dependencies behind each system had to move with it. Mapping them was the first job, and the cutover was built around what the map showed.
The migration plan
We mapped what each system depends on, then built the new platform before anything moved
The dependency mapping tied each hosted system to the access paths and operational requirements around it, and that set the cutover order. We built and tested the Hyper-V environment in the Sydney data centre before any production workload moved.
- Identity and naming Identity services and DNS
- Connectivity and access Network paths, firewall rules, branch connectivity and remote access
- Data and operations Virtual machines, storage, backup, monitoring and support processes
- Destination Hyper-V built and validated in the Sydney data centre
- Cutover Workloads moved in stages onto the tested platform
What we delivered
What the move involved
A Hyper-V platform built and tested in the data centre
The Microsoft Hyper-V environment went up in the Sydney data centre first and was checked against the dependencies we had mapped before any workload moved.
Virtual machines converted and moved in sequence
Each virtual machine was converted for Hyper-V, tested on the new platform and then brought live, working through the estate in a planned order.
Branch and remote access planned into the move
The move was designed around how branches and remote users reach each system, and the network paths and firewall rules from the review went into the cutover plan.
Backup moved with the workloads
Backup was realigned to the new platform and location, and recovery stayed in scope through cutover.
Cutover in stages, then checked in operation
The cutover ran in stages. After go-live we checked the environment in operation, including monitoring and support, and then brought it into our managed infrastructure services.